Shenandoah EAA Chapter 1031

Winchester, VA

Kyle Wallace

Kyle Wallace RV-12is

 2nd Dec 2022

Kyle Wallace (our EAA Chapter Young Eagles coordinator) is building a RV-12is.

All of the empennage and wing sections are completed as of November 28th. The shop is rather crowded at the moment as I haven’t found a safe place for both flaperons yet.

EAA

I started work on the fuselage center section bulkhead and completed the first 6 steps on December 1st, 2022.

EAA

There is a lot of work ahead to complete the fuselage. I will start working on a paint/primer setup so I can switch from rattle cans to a water based epoxy primer. That will eat up more shop space so it will need to be portable. I have the finish kit on order, but the lead time is nearly a year (as of December 1st, 2022). I have to go remind myself what I’m doing.

EAA

March 20th, 2023

I have completed Section 22 Forward Lower Fuselage.  I’m well into Section 23, the Side Skins.  This section also includes all the work on the longerons.  I spent a few days working on the longerons and getting them as close to perfect as I possibly could. They could have been better, but perfection is the enemy of progress.  I have finished prepping all the parts and will be painting them in a large batch soon.  I expect the work required prior to match-drilling the longerons will happen very quickly once the painting is complete.  I couldn’t help myself and I had to cleco the side skins in place just to check how well everything fit together.  I am always mildly amazed when everything lines up and clecos together without any drama.  I expect that this section will be complete before the end of March.  I am excited to rivet on the side skins because I am really getting low on LP4-3 blind rivets.  Every time I pull one, I celebrate that the riveting is that much closer to being finished.  I included a selfie just to prove I’m the one actually building this aircraft.

EAA

EAA

EAA

EAA

May 4th, 2023

There has been a lot of progress recently.  The side skin install was completed.  This was quickly followed by the rollover hoop and rear baggage bulkhead.  This section involved a large number of countersunk rivets that will eventually be underneath the rear window and canopy.   The rollover hoop has to be mounted and unmounted several times to get all the mounts drilled correctly.  Finally, once all the drilling was finished, it was time to paint and then assemble.  Everything went together as easy as pie… it is always a little surprising.  I had hoped to finish before May, but the rear bulkhead and top brace weren’t completed until May Day.  No worries, I was able to prep and assemble the seat backs and braces in two days.  Next week I will be starting on the fuel tank.  

EAA

May 26th, 2023

Fuel tank is fully assembled… it was a pain because there is no place to hold it that doesn’t have a bunch of sealant. Now I’m just waiting until I can pressure test it and see how good a job I actually did.

EAA

EAA

July 26th, 2023

In honor of EAA AirVenture Oshkosh, I have been working on my build rather than having fun in Wisconsin. I just took delivery of the finish kit, but I'm still finishing up the final tasks on the fuselage. Currently, I'm cutting, flaring and bending fuel lines. I really hope these fittings don't leak... I would hate to have to pull these lines after the airframe is fully assembled.

EAA

EAA

EAA

EAA

EAA

August 4th, 2023

The hard fuel lines are all completed. Rudder pedals and brake master cylinders installed. Today I assembled the brake lines. I need to complete the inventory of my Finish Kit, so I will start the forward upper fuselage and instrument panel as soon as I have that finished. I should be on to the flight controls by the middle of the August.

EAA

August 23rd, 2023

The final steps of the RV12is fuselage kit are quickly getting checked off. The forward upper fuselage (avionics bay) is nearly complete. Just a few more dimples and rivets remaining before moving to the finish kit plans. About two days away from starting on the flight controls (already prepped everything that needs paint). I should have control sticks by the end of the month.

EAA

EAA

EAA

EAA

September 13th, 2023

Flight controls are installed and ready for airplane noises... I got the seat cushions, so as soon as I get the landing gear installed, I will jump in and start visualizing the first flight.😀

EAA

EAA

October 12th, 2023

I decided to work on the electrical system and avionics before I install the landing gear. I have found it to be kind of fun... almost finished with both sections now. I will have to defer some of the items until the airframe assembly, but all of the real work is nearly completed. I got the panel today and couldn't resist installing it.
Does the cricket count as my first passenger? I have no idea how it managed to get inside.

EAA

EAA

EAA

EAA

October 20th, 2023

Instrument panel and avionics are finished. The wiring is mostly complete, but I have to wait on a few parts. I have moved onto the landing gear, but I'm also waiting on a few parts before I can put it down on its own legs.

EAA

November 10th, 2023

I have mostly run out of stuff to do unless Van's starts sending me some backordered parts... or a Power Plant kit. It sits on its own legs now. I have even jumped in a few times and tried it on for size. I am considering moving the wings out and installing the tailcone... that would allow me to move forward with the canopy, but I'm still waiting on some of the canopy parts.

EAA

EAA

EAA

December 9th, 2023

Progress has slowed down a bit due to the Van's kit and part shipping shutdown, but I am still managing to get a few things completed here and there...
I will be fitting the wings for the first time very soon... then they will come off and go into storage so I can bring the tail cone back to the workshop. Today was the perfect day, but I could only manage to get the canopy frame fitted. I did crawl under and install the VHF antenna.

EAA

EAA

January 26th, 2024 update

Quick photo dump of mounting the wings for the first time today. John Ely and Juergen Nies came over to help out. It went pretty quickly and very little drama. I was able to match drill the controls for the ailerons. Then it was wings off and back into the workshop. Thanks again to John and Juergen!"

EAA

 EAA

EAA

EAA

EAAEAA

EAA

EAA

EAA

EAA

EAA

 

March 15th, 2024 Update

With a lot of help from John Fontaine and Juergen Nies, we managed to transport my wings to the airport in Winchester. I can't thank them enough, especially John for letting me stash my wings in the back of his hangar. It is difficult to notice from this picture, but the wing spars extend about 3 feet behind the truck bumper... just enough for John to catch his forehead in a very brief moment of distraction. Thanks for helping to keep this build moving forward. I hope the head wound heals quickly. I'm buying the beers at the next hangar party.

EAA

EAA

EAA

EAA

 

April 17th, 2024 Update

I brought the tail cone to the workshop last week so I could temporarily mount it to the center section. There is a service bulletin that wants braces installed on all of the bulkheads in the tail cone. The work isn't hard, it's just drilling out 8 rivets from each bulkhead... the hard part is reaching it in the first place! I had to climb inside the tail cone to drill out 3 of the rivets and replace on each bulkhead. It turned out easier than expected. After the SB was addressed, I decided to try and attach the tail cone. I was prepared to fail and call for help, but it ended up being a smooth mating. The sawhorse isn't holding anything in the final image.

EAA

EAA

EAA

August 18th, 2024 Update

I finished up fitting the tail cone fairing and trimming the stabilator skins for clearance. It was considerably more work than I had expected. I had to install and remove the fiberglass halves at least 20 times, but it came out pretty good. Installing the vertical stabilizer and rudder was frustrating due to clearance for getting the hardware fit. Now the stabilator will go back on the wall until final assembly. I'm still waiting for the power plant kit, so it may be a while.

EAA

EAA

EAA

 October 18th, 2024 Update

I'm on month 14 of waiting for my Power Plant kit to crate, so I'm doing all kinds of odd jobs trying to stay occupied. I just finished up the glare shield. I have run out of interior to paint. Next I will remove the tail cone and get ready for finishing the fuel system that is in the next kit. These are pictures my son wanted for his social media. He said pics of my build have gotten the most likes on his Instagram.

EAA

EAA

EAA

To provide a better user experience, EAA uses cookies. To review EAA's data privacy policy or adjust your privacy settings please visit: Data and Privacy Policy.
loading

Loading...