RV 10 Work Session #20
Several projects continued on the RV-10 today. A lot of time was devoted to fitting and match drilling the rear baggage compartment bulkhead to the forward tail cone bulkhead. Meanwhile, parts from the finish kit were inventoried and Richard continued work on the flap touque tube assembly. Peter and Mark also worked on preparing seat support brackets for installation, while Bob went outside in the cold to prime more parts. The next work sessions will be Thursday evening at 6:30 and Saturday February 15th at 9:00.